A1

Development category

B1

Development (including boundary walls etc.) within 20 metres of the top of a bank of a Main River

C1

Includes culverting or control of flow of any river or stream

D1

Within Flood Zone 3

E1

Within Flood Zone 2

F1

Within Flood Zone 1

A2

Householder development and alterations

B2

Consult EA

Note

C2

Consult EA with FRA showing design details of any culvert or flow control structure proposed

D2

No consultation - see standard comment

Note

E2

No consultation - see standard comment

Note

F2

No consultation - No EA Advice

A3

Non-residential extensions with a footprint of less than 250m2

B3

Consult EA

Note

C3

Consult EA with FRA showing design details of any culvert or flow control structure proposed

D3

No consultation - see standard comment

Note

E3

No consultation - see standard comment

Note

F3

No consultation - No EA Advice

A4

Change of use FROM Water Compatible TO 'Less Vulnerable' development

B4

Only consult EA if site also falls within Flood Zone 3. FRA Required

C4

No consultation - no EA advice

D4

Consult EA with FRA

E4

No consultation - no EA advice

F4

No consultation - No EA Advice

A5

Change of use RESULTING IN 'Highly Vulnerable' or 'More Vulnerable' development

B5

Only consult EA if site also falls within Flood Zone 3 or 2. FRA Required

C5

No consultation - no EA advice

D5

Consult EA with FRA

E5

Consult EA with FRA

F5

No consultation - No EA Advice

A6

Operational development less than 1 hectare

B6

Consult EA

Note

C6

Consult EA with FRA showing design details of any culvert or flow control structure proposed

D6

Consult EA with FRA and Sequential Test Evidence (and where required confirm Exception Test has been applied)

E6

Consult EA with FRA and Sequential Test Evidence (and where required confirm Exception Test has been applied)

F6

No consultation - see standard comment

A7

Operational development of 1 hectare or greater

B7

Consult EA

Note

C7

Consult EA with FRA showing design details of any culvert or flow control structure proposed

D7

Consult EA with FRA and Sequential Test Evidence (and where required confirm Exception Test has been applied)

E7

Consult EA with FRA and Sequential Test Evidence (and where required confirm Exception Test has been applied)

G7

Consult EA with FRA